Comprehensive survey of impacted lands and properties, and marking of boundaries of the DUP area start in Haute-Sanaga on 20 august 2015
20-08-15 11:18
The “Commission de Constat et d’Evaluation” was established on 5 march 2015 by the Governor of Province “Centre” (see decree 41/AR/J/SG dated 5 march 2015) to organize the survey of lands and properties affected by Nachtigal amont Project, and the marking of boundaries of the DUP area. The “sous-commission technique Expertise et Evaluation des biens » was established on 22 june 2015 by the Governor of Province “Centre” (see decree 122/AR/J/SG dated 22 june 2015) to carry on those activities in Haute-Sanaga division. The “sous-commission” visited the site on 2 july 2015 on the initiative of the Senior Divisional Officer (Prefect) of Haute-Sanaga.

The public display of the DUP decree and of the convocation notice of affected people was done on 7 july in Ndokoa village and on 8 july in Minkouma village. The survey and the marking were then authorized 1 month later, say from mid-august. A new information meeting occurred in Ndokoa village on 18 august, before the beginning of the operations on 20 august by the Commission and the Consultants of Nachtigal Project. The operations will be organized in the affected villages and divisions until October 2015.